Commencement notice (Private): No.
Completion notice (Private): Optional.
Preliminary lien notice (Private): Prime contractor - Prior to receiving payment; Subcontractor - 30 days after commencing work.
Pre-lien notice (Private): 20 days prior to filing lien.
Lien claim (Private): Prime contractor - 150 days after the earlier of (1) last day work was performed or (2) the date the project is substantially complete, whichever is earlier; Subcontractor - 120 days after the earlier of (1) last day work was performed or (2) the date the project is substantially complete, whichever is earlier.
Deadline to file suit (Private): 180 days after sending lien statement.
Bonding permitted (Private): Yes, must be 150% of the lien value.
Statutory lien waiver form (Private): Yes.
Special notes: Lien statement must be sent to owner within 5 days after filing lien.