Wisconsin: State-by-State Summary of Construction Liens

Wisconsin

Commencement notice (Private): No.

Completion notice (Private): No.

Preliminary lien notice (Private): Not required.

Pre-lien notice (Private): 30 days prior to filing lien.

Lien claim (Private): 6 months after last performing work.

Deadline to file suit (Private): 2 years after filing lien.

Bonding permitted (Private): Yes, must be 125% of the lien value.

Statutory lien waiver form (Private): No.

Disclaimer: This information was published on January 1, 2020. Please contact Josh Levy, Eric Meier or Samantha Schacht for modifications made by Wisconsin since that date. Visit our 50-State Construction Law Map for information on other states.