South Dakota: State-by-State Summary of Construction Liens

South Dakota

Commencement notice (Private): No.

Completion notice (Private): No.

Preliminary lien notice (Private): Prime contractor - Not required but recommended within 30 days after commencing work; Subcontractor - Not required.

Pre-lien notice (Private): Not required.

Lien claim (Private): 120 days after last furnishing labor/materials.

Deadline to file suit (Private): 6 years after filing lien.

Bonding permitted (Private): Yes, must be 200% of the lien value.

Statutory lien waiver form (Private): No.

Special notes: Time to foreclose lien can be shorted to 30 days after receipt of written demand to file suit.

Disclaimer: This information was published on January 1, 2020. Please contact Josh Levy, Eric Meier or Samantha Schacht for modifications made by South Dakota since that date. Visit our 50-State Construction Law Map for information on other states.