Commencement notice (Private): No.
Completion notice (Private): No.
Preliminary lien notice (Private): Not required.
Pre-lien notice (Private): 10 days prior to filing lien.
Lien claim (Private): 90 days after last furnishing labor/materials.
Deadline to file sui (Private)t: 3 years after filing lien; notice of intent to file suit required 10 days prior.
Bonding permitted (Private): Yes, must be 200% of the lien value.
Statutory lien waiver form (Private): No.
Special notes: Time to foreclose lien can be shorted to 30 days after receipt of written demand to file suit.