Commencement notice (Private): No.
Completion notice (Private): No.
Preliminary lien notice (Private): Not required.
Pre-lien notice (Private): Not required.
Lien claim (Private): 8 months after completing the work.
Deadline to file suit (Private): 1 year after filing lien.
Bonding permitted (Private): Yes, must be 110% of the lien value.
Statutory lien waiver form (Private): No.
Special notes: Time to foreclose lien can be shortened by serving notice specifying time within which claimant must file suit.
Disclaimer: This information was published on January 1, 2020. Please contact Josh Levy, Eric Meier or Samantha Schacht for modifications made by New York since that date. Visit our 50-State Construction Law Map for information on other states.