New Jersey: State-by-State Summary of Construction Liens

New Jersey

Commencement notice (Private): No.

Completion notice (Private): No.

Preliminary lien notice (Private): Not required.

Pre-lien notice (Private): Not required.

Lien claim (Private): 90 days after last furnishing labor/materials.

Deadline to file suit (Private): 1 year after completing work.

Bonding permitted (Private): Yes, must be 110% of the lien value.

Statutory lien waiver form (Private): No.

Special notes: Owner can shorten time to file suit by serving a written demand that a lawsuit be filed within 30 days.

Disclaimer: This information was published on January 1, 2020. Please contact Josh Levy, Eric Meier or Samantha Schacht for modifications made by New Jersey since that date. Visit our 50-State Construction Law Map for information on other states.