Skip to Main Content

Nevada: State-by-State Summary of Construction Liens

Nevada

Commencement notice (Private): No.

Completion notice (Private): Optional.

Preliminary lien notice (Private): Prime contractor - Not required; Subcontractor - 31 days after first furnishing labor/materials.

Pre-lien notice (Private): Not required.

Lien claim (Private): 90 days after latest of completion of the project and last furnishing labor/materials by lien claimant.

Deadline to file suit (Private): 6 months after recording lien.

Bonding permitted (Private): Yes, must be 150% of the lien value.

Statutory lien waiver form (Private): Yes.

Special notes: Time period to file lien is reduced to 40 days if Notice of Completion is recorded.

Disclaimer: This information was published on January 1, 2020. Please contact Josh Levy, Eric Meier or Samantha Schacht for modifications made by Nevada since that date. Visit our 50-State Construction Law Map for information on other states.