Michigan: State-by-State Summary of Prompt Payment

Michigan

Owner to Prime Contractor (Private): N/A

Prime Contractor to Subcontractor (Private): N/A

Interest/Penalties (Private): N/A

Owner to Prime Contractor (Public): The later of (i) 30 days after the architect/engineer certifies the work or (ii) 15 days after the agency has received funds from another applicable agency or government.

Prime Contractor to Subcontractor (Public): N/A

Interest/Penalties (Public): Contractor can include reasonable interest in its next payment request after any untimely payment.

Pay-If-Paid Permissible: Yes.

Disclaimer: This information was published on July 1, 2020. Please contact Josh Levy, Eric Meier or Samantha Schacht for modifications made by Michigan since that date. Visit our 50-State Construction Law Map for information on other states.