Owner to Prime Contractor (Private): N/A
Prime Contractor to Subcontractor (Private): N/A
Interest/Penalties (Private): N/A
Owner to Prime Contractor (Public): The later of (i) 30 days after the architect/engineer certifies the work or (ii) 15 days after the agency has received funds from another applicable agency or government.
Prime Contractor to Subcontractor (Public): N/A
Interest/Penalties (Public): Contractor can include reasonable interest in its next payment request after any untimely payment.
Pay-If-Paid Permissible: Yes.
Disclaimer: This information was published on July 1, 2020. Please contact Josh Levy, Eric Meier or Samantha Schacht for modifications made by Michigan since that date. Visit our 50-State Construction Law Map for information on other states.