Kansas: State-by-State Summary of Construction Liens

Kansas

Commencement notice (Private): No.

Completion notice (Private): No.

Preliminary lien notice (Private): Not required.

Pre-lien notice (Private): Not required.

Lien claim (Private): Prime contractor - 4 months after last furnishing labor/materials; Subcontractor - 3 months after last furnishing labor/materials.

Deadline to file suit (Private): 1 year after recording lien.

Bonding permitted (Private): Yes, must be the amount of the contract price.

Statutory lien waiver form (Private): No.

Disclaimer: This information was published on January 1, 2020. Please contact Josh Levy, Eric Meier or Samantha Schacht for modifications made by Kansas since that date. Visit our 50-State Construction Law Map for information on other states.