Alabama: State-by-State Summary of Construction Liens

Alabama

Commencement notice (Private): No.

Completion notice (Private): No.

Preliminary lien notice (Private): Prime contractor - Not required; Subcontractor - Not required but recommended. Serve prior to commencing work.

Pre-lien notice (Private): Prime contractor - Not required; Subcontractor - Prior to filing lien claim.

Lien claim (Private): Prime contractor - 6 months after last furnishing labor/materials; Subcontractor - 4 months after last furnishing labor/materials.

Deadline to file suit (Private): 6 months after last furnishing labor/materials.

Bonding permitted (Private): Yes, must be 100% of the lien value plus interest thereon at 8% per year for three years plus $100.

Statutory lien waiver form (Private): No.

Disclaimer: This information was published on January 1, 2020. Please contact Josh Levy, Eric Meier or Samantha Schacht for modifications made by Alabama since that date. Visit our 50-State Construction Law Map for information on other states.